The Harbor
What is the Harbor siding project?
The scope of work includes the removal of old siding, fascia, soffit and gutters, followed by the installation of new materials to improve both functionality and aesthetics, ensuring proper weatherproofing and drainage.
Our team will also inspect the structure for damage, provide necessary repairs, and finish with a clean, high-quality installation.
Siding Selection: James Hardie Cobblestone
Recent Project Updates
Monday April 28th
Building #9 Demolition begins. Re-siding estimated to take 4 weeks.
Monday May 12th
Demolition on buildings #7 and #8 begins. Re-siding estimated to take 3 weeks.
Monday June 16th
Wrapping up all work including final gutters and windows. Project will remain on pause for the summer and resume in September!
Progress Photos
Meet The Team
Brian Campbell
Project Development
Matt Cerick
Project Manager
Butch Hoffman
Site Supervisor
Project Schedule
This project will be completed in two phases as shown on the map below.