The Harbor

Check back for updates on your neighborhood project.

What is the Harbor siding project?

The scope of work includes the removal of old siding, fascia, soffit and gutters, followed by the installation of new materials to improve both functionality and aesthetics, ensuring proper weatherproofing and drainage.

Our team will also inspect the structure for damage, provide necessary repairs, and finish with a clean, high-quality installation.

Siding Selection: James Hardie Cobblestone

Recent Project Updates

Wednesday April 2nd

Demolition on building #12 begins. Re-siding estimated to take 4 weeks.

Monday April 14th

Building 13 to wrap up this week. Buildings 12 & 11 on track. Demo on building 10 to begin once Building 13 is complete.

Progress Photos

Meet The Team

Brian Campbell
Project Development
Matt Cerick
Project Manager
Butch Hoffman
Site Supervisor

Project Schedule

This project will be completed in two phases as shown on the map below.

Phase 1: March, April, May

  1. Building # 15 – Mock Building
  2. Then buildings 14, 13, 12, 11, 10, 9, 8, 7
  3. Materials will be place outside buildings # 12 & 7

Phase 2: Sept, Oct, Nov

  1. Buildings 1, 2, 3, 4, 5, 6, 16
  2. Materials will be placed outside buildings #12 & 4