The Harbor

Check back for updates on your neighborhood project.

What is the Harbor siding project?

The scope of work includes the removal of old siding, fascia, soffit and gutters, followed by the installation of new materials to improve both functionality and aesthetics, ensuring proper weatherproofing and drainage.

Our team will also inspect the structure for damage, provide necessary repairs, and finish with a clean, high-quality installation.

Siding Selection: James Hardie Cobblestone

Project Updates

Monday March 24th

Tentative start date for building #14 demolition.

March 17th – 21st

New siding to be installed on building #15. The Board will review the installation and product selection, and make any changes before starting building #14.

Monday March, 10th

Demo started at building #15. Discovered rotten sheathing and framing, communicated to the HOA. Repairs are being made before re-siding begins.

Rot shown on sheathing

Friday March, 7th

Siding was delivered on site.

Materials Delivered

Thursday February 27th

Open house for The Harbor project at the Highmark office. From 5:00 – 6:30pm residents are welcome to join us for a social hour, project walkthrough, and Q&A.

Watch Meeting Recording

Meet The Team

Brian Campbell
Project Development
Matt Cerick
Project Manager
Butch Hoffman
Site Supervisor

Project Schedule

This project will be completed in two phases as shown on the map below.

Phase 1: March, April, May

  1. Building # 15 – Mock Building
  2. Then buildings 14, 13, 12, 11, 10, 9, 8, 7
  3. Materials will be place outside buildings # 12 & 7

Phase 2: Sept, Oct, Nov

  1. Buildings 1, 2, 3, 4, 5, 6, 16
  2. Materials will be placed outside buildings #12 & 4